Crews from Ballard Marine Construction began work Tuesday morning to replace three pilings at the dock at Steamboat Landing Marine Park. The structures were damaged last summer as a result of what city officials believe was a boat crashing into the dock. Due to fish spawing patterns in the Columbia River, the work must be completed by Jan. 1.

Work began today to replace three pilings on a dock at Steamboat Landing Waterfront Park that were damaged in the summer.

On Dec. 21, the Washougal City Council unanimously approved a $26,016 contract with Washougal-based Ballard Marine Construction to make the repairs.